FROM HRP SB TO MIL over HUTCHINSON RIVER

EXIT 9B HRP TO MILL RDC82 · County 119, New York · Built 1990 · 1 Lanes · 3,828 vehicles/day

Overall
Good
Culvert
7
Good

Bridge Details

Structure #
000000005523580
Year Built
1990
Length
12.8 m (42 ft)
Max Span
12.4 m
Lanes
1
Daily Traffic
3,828
Material
Concrete
Design
Culvert
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$277,000
Total Project Cost
$439,000