RTE 305 over DEER CREEK

1.9 MI NE PORTVILLE N Y · County 009, New York · Built 1945 · 2 Lanes · 2,597 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
4
Poor
Superstructure
4
Poor
Substructure
7
Good

Bridge Details

Structure #
000000001045440
Year Built
1945
Length
10.7 m (35.1 ft)
Max Span
10 m
Width
11.6 m (38.1 ft)
Lanes
2
Daily Traffic
2,597
Material
Concrete
Design
Slab
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$662,000
Total Project Cost
$1,049,000