RTE 18F over ROBERT MOSES PKWY ROBER

.2 MI N JCT SH 18 & SH18F · County 063, New York · Built 1967 · 2 Lanes · 457 vehicles/day

Overall
Fair
Deck
8
Very Good
Superstructure
6
Satisfactory
Substructure
7
Good

Bridge Details

Structure #
000000001014880
Year Built
1967
Reconstructed
1995
Length
72.2 m (236.9 ft)
Max Span
35.6 m
Width
10.1 m (33.1 ft)
Lanes
2
Daily Traffic
457
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
State Park, Forest, or Reservation Agency
Last Inspected
N/A
Est. Improvement
$3,353,000
Total Project Cost
$5,317,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.