Baldwin Avenue over Conrail & Path

0.4 MI S of RT 139 · County 017, New Jersey · Built 1917 · 2 Lanes · 38,705 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
4
Poor
Superstructure
4
Poor
Substructure
4
Poor

Bridge Details

Structure #
0954163
Year Built
1917
Reconstructed
1990
Length
50.6 m (166 ft)
Max Span
21.9 m
Width
10.3 m (33.8 ft)
Lanes
2
Daily Traffic
38,705
Material
Steel
Design
Girder and Floorbeam System
Owner
Unknown
Last Inspected
N/A
Est. Improvement
$2,509,000
Total Project Cost
$5,863,000