I-93 SB over US 3

1.74 MI N WOODSTOCK TL · County 009, New Hampshire · Built 1973 · 3 Lanes · 5,785 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Bridge Details

Structure #
014802010009300
Year Built
1973
Reconstructed
1982
Length
38.4 m (126 ft)
Max Span
36.6 m
Width
21 m (68.9 ft)
Lanes
3
Daily Traffic
5,785
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$272,000
Total Project Cost
$314,000