I-89 NB over NH 10

2.1 MI FROM SPRINGFIELD T · County 019, New Hampshire · Built 1967 · 2 Lanes · 10,804 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
5
Fair

Condition Ratings

ComponentRatingDescription
Deck 6 Satisfactory
Superstructure 6 Satisfactory
Substructure 5 Fair

Location

43.498814, -72.132594

This bridge is in worse condition than 73.4% of bridges in County 019. The average bridge in New Hampshire is 0 years old; this one is 59 years old.

Nearby Bridges

Bridge Details

Structure #
010001170008300
Year Built
1967
Length
27.3 m (89.6 ft)
Max Span
25.6 m
Width
13.4 m (44 ft)
Lanes
2
Daily Traffic
10,804
Material
Prestressed Concrete
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$272,000
Total Project Cost
$314,000