I 215 BELTWAY over SPENCER STREET

LAS VEGAS · County 003, Nevada · Built 1996 · 4 Lanes · 77,000 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
7
Good
Substructure
7
Good

Condition Ratings

ComponentRatingDescription
Deck 6 Satisfactory
Superstructure 7 Good
Substructure 7 Good

Location

36.025583, -115.127347

This bridge is in worse condition than 82.9% of bridges in County 003. The average bridge in Nevada is 0 years old; this one is 30 years old.

Nearby Bridges

Bridge Details

Structure #
H2079S
Year Built
1996
Length
58.5 m (191.9 ft)
Max Span
28.3 m
Width
22.7 m (74.5 ft)
Lanes
4
Daily Traffic
77,000
Material
Prestressed Concrete Continuous
Design
Box Beam or Girders - Single or Spread
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
N/A
Total Project Cost
N/A
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.