N5 over BIG SANDY CREEK
11N DESHLER · County 169, Nebraska · Built 2005 · 2 Lanes · 420 vehicles/day
Overall
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
8
Very Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 8 | Very Good |
| Superstructure | 8 | Very Good |
| Substructure | 8 | Very Good |
Location
40.299828, -97.726875
This bridge is in worse condition than 23.6% of bridges in County 169. The average bridge in Nebraska is 0 years old; this one is 21 years old.
Nearby Bridges
ROAD 5500 over BIG SANDY CREEK
Built 1935
COUNTY HIGHWAY over BIG SANDY CREEK
Built 1935
N4 over STREAM
Built 1962
N4 over BIG SANDY CREEK
Built 1962
RD 5200 over BIG SANDY CREEK
Built 2023
COUNTY HIGHWAY over BIG SANDY CREEK
Built 1968
ROAD 5700 over BIG SANDY CREEK
Built 1935
COUNTY HIGHWAY over BIG SANDY CREEK
Built 1966
N4 over STREAM
Built 1962
COUNTY HIGHWAY over STREAM
Built 1935
Bridge Details
- Structure #
- S005 01050
- Year Built
- 2005
- Length
- 40.2 m (131.9 ft)
- Max Span
- 15.8 m
- Width
- 12.9 m (42.3 ft)
- Lanes
- 2
- Daily Traffic
- 420
- Material
- Prestressed Concrete Continuous
- Design
- Tee Beam
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $0
- Total Project Cost
- $0