THEONY RD over ROCK CREEK 031

23M W OPHEIM · County 105, Montana · Built 2013 · 2 Lanes · 14 vehicles/day

Overall
Fair
Deck
7
Good
Superstructure
7
Good
Substructure
6
Satisfactory

Condition Ratings

ComponentRatingDescription
Deck 7 Good
Superstructure 7 Good
Substructure 6 Satisfactory

Location

48.880214, -106.901122

This bridge is in worse condition than 24.3% of bridges in County 105. The average bridge in Montana is 0 years old; this one is 13 years old.

Nearby Bridges

Bridge Details

Structure #
L53001020+07001
Year Built
2013
Length
66.8 m (219.2 ft)
Max Span
33.3 m
Width
8.3 m (27.2 ft)
Lanes
2
Daily Traffic
14
Material
Prestressed Concrete
Design
Tee Beam
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$340,000
Total Project Cost
$510,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.