CANYON MILL RD over PABLO FEEDER CANAL 008
2M NW RONAN · County 047, Montana · Built 2014 · 2 Lanes · 100 vehicles/day
Overall
Deck
8
Very Good
Superstructure
7
Good
Substructure
8
Very Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 8 | Very Good |
| Superstructure | 7 | Good |
| Substructure | 8 | Very Good |
Location
47.573336, -114.060475
This bridge is in worse condition than 28.4% of bridges in County 047. The average bridge in Montana is 0 years old; this one is 12 years old.
Nearby Bridges
N CROW RD over PABLO FEEDER CANAL 007
Built 1978
EMORY RD over PABLO FEEDER CANAL 025
Built 2018
MICHAEL RD over PABLO FEEDER CANAL 024
Built 2014
US 93 over MUD CREEK
Built 2008
OLD US HWY 93 over MUD CREEK 097
Built 2007
US 93 over MUD CREEK
Built 2007
US 93 over WILDLIFE CROSSING
Built 2007
US 93 over AGRICULTURAL CROSSING
Built 2007
US 93 over WILDLIFE CROSSING
Built 2007
TERRACE LAKE RD over N CROW CREEK 021
Built 1965
Bridge Details
- Structure #
- L24623002+03001
- Year Built
- 2014
- Length
- 15.4 m (50.5 ft)
- Max Span
- 14 m
- Width
- 6.3 m (20.7 ft)
- Lanes
- 2
- Daily Traffic
- 100
- Material
- Steel
- Design
- Stringer/Multi-beam or Girder
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- N/A
- Total Project Cost
- N/A
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.