TULLOCK CR RD over TULLOCK CREEK 029

15M NE HARDIN · County 003, Montana · Built 2006 · 2 Lanes · 34 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
7
Good
Substructure
7
Good

Condition Ratings

ComponentRatingDescription
Deck 6 Satisfactory
Superstructure 7 Good
Substructure 7 Good

Location

45.873464, -107.327064

This bridge is in worse condition than 36.1% of bridges in County 003. The average bridge in Montana is 0 years old; this one is 20 years old.

Nearby Bridges

Bridge Details

Structure #
L02002006+05001
Year Built
2006
Length
20.1 m (65.9 ft)
Max Span
20.1 m
Width
9.2 m (30.2 ft)
Lanes
2
Daily Traffic
34
Material
Prestressed Concrete
Design
Tee Beam
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$50,000
Total Project Cost
$62,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.