IRR - S 313 over WILLIAMS COULEE
1M S HARDIN · County 003, Montana · Built 2021 · 2 Lanes · 899 vehicles/day
Overall
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 7 | Good |
| Substructure | 7 | Good |
Location
45.703881, -107.621931
This bridge is in worse condition than 13.5% of bridges in County 003. The average bridge in Montana is 0 years old; this one is 5 years old.
Nearby Bridges
RAIL RD over TWO LEGGINS CANAL
Built 2021
Randall Road over Two Leggins Canal
Built 2024
PERITSA CREEK RD over TWO LEGGIN`S CANAL 048
Built 2014
OLD HWY 87 over TWO LEGGINS CANAL 0
Built 1931
VANZANDT RD over TWO LEGGIN`S CANAL 047
Built 1994
IRR - S 313 over TWO LEGGIN CANAL
Built 1989
IRR-S 47 over INT W HARDIN I 90
Built 1970
IRR - I 90 over RR (NOT IN USE)
Built 1971
IRR - I 90 over RR (NOT IN USE)
Built 1971
I 90 FRONTAGE RD over BIGHORN RIVER
Built 2007
Bridge Details
- Structure #
- 000000202106632
- Year Built
- 2021
- Length
- 22.3 m (73.2 ft)
- Max Span
- 8.5 m
- Width
- 10.8 m (35.4 ft)
- Lanes
- 2
- Daily Traffic
- 899
- Material
- Concrete
- Design
- Slab
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- N/A
- Total Project Cost
- N/A
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.