US 50 W over MOREAU RVR
S 23 T 44 N R 11 W · County 051, Missouri · Built 1984 · 2 Lanes · 9,565 vehicles/day
Structurally Deficient
— One or more key components rated 4 (Poor) or below
Overall
Deck
6
Satisfactory
Superstructure
4
Poor
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 4 | Poor |
| Substructure | 6 | Satisfactory |
Location
38.540811, -92.106103
This bridge is in worse condition than 90.7% of bridges in County 051. The average bridge in Missouri is 0 years old; this one is 42 years old.
Nearby Bridges
US 50 E over MOREAU RVR
Built 1960
E MCCARTY ST E over US 50
Built 2007
ALGOA RD over MOREAU RIVER
Built 1992
MILITIA DR S over RISING CR
Built 1997
PARTNERSHIP BLVD over RISING CREEK
Built 2006
SHAMROCK RD over RISING CR
Built 1991
ALGOA RD over RISING CREEK
Built 1955
BALD HILL RD over MOREAU RVR
Built 1988
US 50 E over RISING CR
Built 1977
EASTLAND DR over BOGGS CREEK
Built 1981
Bridge Details
- Structure #
- 3558
- Year Built
- 1984
- Length
- 145.4 m (477 ft)
- Max Span
- 45.7 m
- Width
- 12.6 m (41.3 ft)
- Lanes
- 2
- Daily Traffic
- 9,565
- Material
- Steel Continuous
- Design
- Stringer/Multi-beam or Girder
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $2,082,000
- Total Project Cost
- $3,123,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.