JAVA RD over BEAR CR

S 33 T 59 N R 19 W · County 115, Missouri · Built 1940 · 1 Lanes · 5 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
7
Good
Superstructure
6
Satisfactory
Substructure
4
Poor

Condition Ratings

ComponentRatingDescription
Deck 7 Good
Superstructure 6 Satisfactory
Substructure 4 Poor

Location

39.88215, -93.02905

This bridge is in worse condition than 82.4% of bridges in County 115. The average bridge in Missouri is 0 years old; this one is 86 years old.

Nearby Bridges

Bridge Details

Structure #
24565
Year Built
1940
Reconstructed
2012
Length
14 m (45.9 ft)
Max Span
8.5 m
Width
4.9 m (16.1 ft)
Lanes
1
Daily Traffic
5
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$255,000
Total Project Cost
$383,000