E 130 ST over ZADIES CR

S 14 T 66 N R 27 W · County 081, Missouri · Built 1960 · 1 Lanes · 15 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
7
Good
Superstructure
6
Satisfactory
Substructure
4
Poor

Bridge Details

Structure #
15863
Year Built
1960
Reconstructed
1983
Length
9.1 m (29.9 ft)
Max Span
8.5 m
Width
4.5 m (14.8 ft)
Lanes
1
Daily Traffic
15
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$192,000
Total Project Cost
$289,000