ST. THOMAS ROAD over RELIEF FOR BAKERS CREEK

SEC 30 T 6N R 2W B · County 049, Mississippi · Built 1982 · 2 Lanes · 150 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Serious
Deck
4
Poor
Superstructure
4
Poor
Substructure
2
Critical

Bridge Details

Structure #
SA2500000000292
Year Built
1982
Length
34.7 m (113.8 ft)
Max Span
5.8 m
Width
8.5 m (27.9 ft)
Lanes
2
Daily Traffic
150
Material
Concrete
Design
Channel Beam
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$255,000
Total Project Cost
$314,000