T 274 over SUGAR CREEK

1.1 MI NW OF JCT CSAH 8 · County 045, Minnesota · Built 1992 · 2 Lanes · 19 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
6
Satisfactory

Condition Ratings

ComponentRatingDescription
Deck 6 Satisfactory
Superstructure 6 Satisfactory
Substructure 6 Satisfactory

Location

43.760383, -92.154997

This bridge is in worse condition than 71.6% of bridges in County 045. The average bridge in Minnesota is 0 years old; this one is 34 years old.

Nearby Bridges

Bridge Details

Structure #
23549
Year Built
1992
Length
26.9 m (88.3 ft)
Max Span
9.8 m
Width
9.5 m (31.2 ft)
Lanes
2
Daily Traffic
19
Material
Concrete Continuous
Design
Slab
Owner
Town or Township Highway Agency
Last Inspected
N/A
Est. Improvement
$274,000,000
Total Project Cost
N/A