I-75 NB over STONY CREEK

3.2 MI NE OF M-50 · County 115, Michigan · Built 2015 · 4 Lanes · 36,850 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
8
Very Good
Substructure
7
Good

Condition Ratings

ComponentRatingDescription
Deck 7 Good
Superstructure 8 Very Good
Substructure 7 Good

Location

41.968883, -83.346386

This bridge is in worse condition than 28.8% of bridges in County 115. The average bridge in Michigan is 0 years old; this one is 11 years old.

Nearby Bridges

Bridge Details

Structure #
000000000007189
Year Built
2015
Length
53 m (173.9 ft)
Max Span
26 m
Width
23.4 m (76.8 ft)
Lanes
4
Daily Traffic
36,850
Material
Prestressed Concrete
Design
Box Beam or Girders - Single or Spread
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
N/A
Total Project Cost
N/A