NORTH AVENUE over WABASCON CREEK
3 MI W OF ASSYRIA · County 015, Michigan · Built 2020 · 2 Lanes · 1,000 vehicles/day
Overall
Deck
8
Very Good
Superstructure
7
Good
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 8 | Very Good |
| Superstructure | 7 | Good |
| Substructure | 6 | Satisfactory |
Location
42.452233, -85.180461
This bridge is in worse condition than 62.3% of bridges in County 015. The average bridge in Michigan is 0 years old; this one is 6 years old.
Nearby Bridges
BASELINE ROAD over WANONDOGER CREEK
Built 1980
M-66 over WANADOGA CREEK
Built 1933
HUFF ROAD over WANADOGA CREEK
Built 1970
JONES ROAD over WANADOGA CREEK
Built 1970
3 1/2 MILE ROAD over WABASCON CREEK
Built 1973
TASKER RD over WANADOGA CREEK
Built 1970
PIFER ROAD over HIGH BANK CREEK
Built 1996
M-66 over WANADOGA CREEK
Built 2012
BUTLER ROAD over HIGH BANKS CREEK
Built 1970
HALBERT RD over WABASCON CREEK
Built 2019
Bridge Details
- Structure #
- 000000000000559
- Year Built
- 2020
- Length
- 8.5 m (27.9 ft)
- Max Span
- 8.2 m
- Width
- 10.4 m (34.1 ft)
- Lanes
- 2
- Daily Traffic
- 1,000
- Material
- Wood or Timber
- Design
- Slab
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $115,000
- Total Project Cost
- $130,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.