GUSTIN RD over JIMMY POND INLET

.1 MI E WENTZEL RD · County 011, Maine · Built 2024 · 2 Lanes · 54 vehicles/day

Overall
Good
Deck
9
Excellent
Superstructure
8
Very Good
Substructure
9
Excellent

Condition Ratings

ComponentRatingDescription
Deck 9 Excellent
Superstructure 8 Very Good
Substructure 9 Excellent

Location

44.14685, -70.004031

This bridge is in worse condition than 15.8% of bridges in County 011. The average bridge in Maine is 0 years old; this one is 2 years old.

Nearby Bridges

Bridge Details

Structure #
0488
Year Built
2024
Length
15.3 m (50.2 ft)
Max Span
14.6 m
Width
5.5 m (18 ft)
Lanes
2
Daily Traffic
54
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
Town or Township Highway Agency
Last Inspected
N/A
Est. Improvement
N/A
Total Project Cost
N/A