1ST AVE over CLEAR CREEK

000000000 · County 103, Iowa · Built 1969 · 5 Lanes · 23,500 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
8
Very Good

Condition Ratings

ComponentRatingDescription
Deck 8 Very Good
Superstructure 8 Very Good
Substructure 8 Very Good

Location

41.670375, -91.565467

This bridge is in worse condition than 28.5% of bridges in County 103. The average bridge in Iowa is 0 years old; this one is 57 years old.

Nearby Bridges

Bridge Details

Structure #
000000000002580
Year Built
1969
Reconstructed
2010
Length
45.7 m (149.9 ft)
Max Span
18 m
Width
29.9 m (98.1 ft)
Lanes
5
Daily Traffic
23,500
Material
Concrete Continuous
Design
Slab
Owner
City or Municipal Highway Agency
Last Inspected
N/A
Est. Improvement
$605,000
Total Project Cost
$667,000