NEW HARMONY ROAD over TRIBUTARY OF SQUAW CREEK
0.42 MI W WEYERBACHER · County 173, Indiana · Built 1979 · 2 Lanes · 205 vehicles/day
Structurally Deficient
— One or more key components rated 4 (Poor) or below
Overall
Culvert
3
Serious
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Culvert | 3 | Serious |
Location
38.092, -87.365275
This bridge is in worse condition than 98.5% of bridges in County 173. The average bridge in Indiana is 0 years old; this one is 47 years old.
Nearby Bridges
STATE STREET over SQUAW CREEK
Built 1976
NEW HARMONY ROAD over SQUAW CREEK
Built 1990
INDERRIEDEN ROAD over SQUAW CREEK
Built 1979
NEW HARMONY ROAD over PIGEON CREEK
Built 1959
NEW HARMONY ROAD over TRIBUTARY OF PIGEON CREE
Built 1930
STATE STREET over WRIGHT DITCH
Built 1978
FARLEY ROAD over TRIBUTARY OF PIGEON CREE
Built 1996
INDERRIEDEN ROAD over WRIGHT DITCH
Built 1965
NEW HARMONY ROAD over CYPRESS CREEK
Built 1969
SR 61 over CYPRESS CREEK
Built 2018
Bridge Details
- Structure #
- 8700043
- Year Built
- 1979
- Length
- 9.9 m (32.5 ft)
- Max Span
- 3.5 m
- Width
- 7.3 m (24 ft)
- Lanes
- 2
- Daily Traffic
- 205
- Material
- Steel
- Design
- Culvert
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $713,000
- Total Project Cost
- $1,073,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.