213TH STREET over HART DITCH

00.10 W. of CALUMET AVE · County 089, Indiana · Built 1955 · 2 Lanes · 5,782 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
4
Poor
Superstructure
4
Poor
Substructure
5
Fair

Bridge Details

Structure #
4500152
Year Built
1955
Length
25 m (82 ft)
Max Span
9.6 m
Width
9.7 m (31.8 ft)
Lanes
2
Daily Traffic
5,782
Material
Concrete Continuous
Design
Slab
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$1,176,000
Total Project Cost
$2,352,000