HOAGLAND RD over ADAM SCHLEMMER BAKER DRA
00.40 E OF MCARDLE RD · County 003, Indiana · Built 1930 · 2 Lanes · 338 vehicles/day
Overall
Deck
5
Fair
Superstructure
5
Fair
Substructure
5
Fair
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 5 | Fair |
| Superstructure | 5 | Fair |
| Substructure | 5 | Fair |
Location
40.950033, -84.867453
This bridge is in worse condition than 76.3% of bridges in County 003. The average bridge in Indiana is 0 years old; this one is 96 years old.
Nearby Bridges
MCARDLE RD over ADAM SCHLEMMER BAKER DRA
Built 1975
MCARDLE RD over ADAM SCHLEMMER BAKER DRA
Built 1973
SR 101 over Branch of Brown Ditch
Built 1980
FLATROCK RD over ADAM SCHLEMMER BAKER DRA
Built 1973
BARKLEY RD over BROWN DRAIN
Built 1975
SR 101 over Brown Ditch
Built 1956
LORTIE RD over FLATROCK CREEK
Built 1989
FLATROCK RD over BOHNKE DRAIN
Built 2014
CLAYTON RD over BOHNKE DRAIN
Built 1972
MONROEVILLE RD over FLATROCK CREEK
Built 1975
Bridge Details
- Structure #
- 0200288
- Year Built
- 1930
- Reconstructed
- 1970
- Length
- 9.4 m (30.8 ft)
- Max Span
- 7.3 m
- Width
- 7.3 m (24 ft)
- Lanes
- 2
- Daily Traffic
- 338
- Material
- Prestressed Concrete
- Design
- Box Beam or Girders - Multiple
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $525,000
- Total Project Cost
- $950,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.