US 12 20 45 MANNHE over RR - UP PROVISO YD

0.3 M S US 20 · County 031, Illinois · Built 1954 · 4 Lanes · 43,600 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
8
Very Good
Substructure
6
Satisfactory

Bridge Details

Structure #
016033700000000
Year Built
1954
Reconstructed
1998
Length
429.2 m (1408.1 ft)
Max Span
36.6 m
Width
21.9 m (71.9 ft)
Lanes
4
Daily Traffic
43,600
Material
Steel Continuous
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$5,745,000
Total Project Cost
$8,617,000