STC5727;RAMSEY RD over BNSF RR; DIAGONAL RD
5.2 N. HAYDEN · County 055, Idaho · Built 2021 · 2 Lanes · 5,100 vehicles/day
Overall
Deck
7
Good
Superstructure
8
Very Good
Substructure
8
Very Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 8 | Very Good |
| Substructure | 8 | Very Good |
Location
47.863694, -116.80825
This bridge is in worse condition than 15.7% of bridges in County 055. The average bridge in Idaho is 0 years old; this one is 5 years old.
Nearby Bridges
ABBOTT ROAD over OLD US 95/UPRR
Built 2013
ABBOTT ROAD over US 95;ABBOTT RD IC
Built 2013
GARWOOD RD over US 95; UPRR; OLD US 95
Built 2022
SH 53 over UPRR
Built 2020
SH 53 over US 95
Built 2020
US 95 over WILDLIFE CROSSING
Built 2012
SH 41 over BURLINGTON NORTHERN RR
Built 2014
BUNCO ROAD over BUNCO RD; US 95 IC
Built 2012
STC 5736;HAYDEN LK over HAYDEN CREEK
Built 1987
STC5751;OLD HWY 95 over SIRR & UPRR;S.ATHOL OP
Built 1929
Bridge Details
- Structure #
- 000000000037040
- Year Built
- 2021
- Length
- 119.8 m (393 ft)
- Max Span
- 39.3 m
- Width
- 15.8 m (51.8 ft)
- Lanes
- 2
- Daily Traffic
- 5,100
- Material
- Prestressed Concrete
- Design
- Tee Beam
- Owner
- Other Local Agencies
- Last Inspected
- N/A
- Est. Improvement
- $3,158,000
- Total Project Cost
- $4,737,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.