2300 EAST ROAD over MILNER GOODING CANAL
3.0 N. 3.4 E. HAZELTON · County 053, Idaho · Built 1975 · 2 Lanes · 90 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
5
Fair
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 6 | Satisfactory |
| Substructure | 5 | Fair |
Location
42.641528, -114.069583
This bridge is in worse condition than 75.7% of bridges in County 053. The average bridge in Idaho is 0 years old; this one is 51 years old.
Nearby Bridges
2200 EAST ROAD over T.F.NORTHSIDE MAIN CNL
Built 1969
2100 EAST ROAD over C CANAL
Built 1975
SH 25; RIDGEWAY RD over I 84;RIDGEWAY ROAD IC
Built 1966
990 SOUTH ROAD over T.F.NORTHSIDE MAIN CNL
Built 1928
1010 SOUTH ROAD over T.F.NORTHSIDE MAIN CNL
Built 1966
1010 SOUTH ROAD over C CANAL
Built 1965
I 84 WBL over MAIN NORTHSIDE CANAL
Built 1966
I 84 WBL over C CANAL
Built 1966
I 84 EBL over MAIN NORTHSIDE CANAL
Built 1966
I 84 EBL over C CANAL
Built 1966
Bridge Details
- Structure #
- 000000000024560
- Year Built
- 1975
- Length
- 23.8 m (78.1 ft)
- Max Span
- 23.5 m
- Width
- 7.3 m (24 ft)
- Lanes
- 2
- Daily Traffic
- 90
- Material
- Prestressed Concrete
- Design
- Tee Beam
- Owner
- Other Local Agencies
- Last Inspected
- N/A
- Est. Improvement
- $510,000
- Total Project Cost
- $765,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.