I 90 over TIMOTHY LN;EVERGREEN GS
4.0E. 4.0S. COEUR DALENE · County 055, Idaho · Built 1992 · 4 Lanes · 18,500 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
8
Very Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 8 | Very Good |
| Substructure | 7 | Good |
Location
47.638261, -116.707697
This bridge is in worse condition than 34.6% of bridges in County 055. The average bridge in Idaho is 0 years old; this one is 34 years old.
Nearby Bridges
YELLOWSTONE TRAIL over I90;YELLOWSTONE TRAIL GS
Built 1991
I 90 over BENNETT BAY;SUNNYSIDE RD
Built 1991
I 90 over BLUE CREEK BAY WEST GS
Built 1992
MULLAN TRAIL RD over I90;MULLAN TRAIL RD IC
Built 1991
I 90 EBL over CDA LAKE;BLUE CREEK BAY
Built 1972
I 90 WBL over CDA LAKE;BLUE CREEK BAY
Built 1951
SH 97 over BEAUTY CREEK
Built 2009
POTLATCH HILL ROAD over SMA 7235;POTLATCH RD GS
Built 1960
STC5745;E.FERNAN L over FERNAN LAKE
Built 2010
SH 97 over I90 EB-WB; WOLF LODGE IC
Built 2016
Bridge Details
- Structure #
- 000000000016897
- Year Built
- 1992
- Length
- 64.3 m (211 ft)
- Max Span
- 25.9 m
- Width
- 25.5 m (83.7 ft)
- Lanes
- 4
- Daily Traffic
- 18,500
- Material
- Prestressed Concrete
- Design
- Stringer/Multi-beam or Girder
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $3,274,000
- Total Project Cost
- $4,911,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.