CR 78 BAUGHS CROSS over MUD CREEK
6 MI S OF LAGRANGE · County 285, Georgia · Built 2015 · 2 Lanes · 350 vehicles/day
Overall
Deck
8
Very Good
Superstructure
7
Good
Substructure
8
Very Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 8 | Very Good |
| Superstructure | 7 | Good |
| Substructure | 8 | Very Good |
Location
32.918219, -85.032822
This bridge is in worse condition than 26.8% of bridges in County 285. The average bridge in Georgia is 0 years old; this one is 11 years old.
Nearby Bridges
SR 219 over MUD CREEK
Built 1960
SR 219 over FLAT SHOALS CREEK
Built 1960
SR 219 over WILDCAT CREEK
Built 1960
CR 415 SALEM ROAD over FLAT SHOAL CREEK
Built 2015
BILL TAYLOR ROAD over WILDCAT CREEK
Built 2019
SALEM ROAD over POLECAT CREEK
Built 1985
SR 18 over FLAT SHOALS CREEK
Built 1963
ADAMS ROAD over BIG BRANCH
Built 1970
SR 219 over LONG CANE CREEK
Built 1992
DENNIS SMITH ROAD over INGRAM CREEK
Built 2003
Bridge Details
- Structure #
- 000000028550780
- Year Built
- 2015
- Length
- 27.4 m (89.9 ft)
- Max Span
- 27.4 m
- Width
- 10.2 m (33.5 ft)
- Lanes
- 2
- Daily Traffic
- 350
- Material
- Prestressed Concrete
- Design
- Stringer/Multi-beam or Girder
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $7,992,000
- Total Project Cost
- $11,988,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.