STAGE COACH ROAD over BARNETTS CREEK
APP 9.4 MILES NORTHEAST · County 131, Georgia · Built 2014 · 2 Lanes · 30 vehicles/day
Overall
Deck
7
Good
Superstructure
8
Very Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 8 | Very Good |
| Substructure | 7 | Good |
Location
31.0072, -84.129731
This bridge is in worse condition than 37.5% of bridges in County 131. The average bridge in Georgia is 0 years old; this one is 12 years old.
Nearby Bridges
LEE WHITE ROAD over E BR. OF BARNETTS CRK
Built 1984
MALLOY ROAD over E BR OF BARNETTS CRK
Built 2003
SR 111 over BARNETTS CREEK
Built 1991
JACK ARCH BANKS RD over BARNETTS CREEK
Built 1978
TISHA COOPER RD over E BR. OF BARNETTS CRK
Built 1960
TISHA COOPER RD over E BR OF BARNETTS CRK TR
Built 1993
DOLLAR STORE RD over BARNETTS CREEK
Built 1970
NOLES ROAD over BIG BRANCH
Built 2005
UNION HILL ROAD over SPENCE MILL CREEK
Built 1988
SR 111 over W BRANCH BARNETTS CREEK
Built 1991
Bridge Details
- Structure #
- 000000013151090
- Year Built
- 2014
- Length
- 74.1 m (243.1 ft)
- Max Span
- 32.9 m
- Width
- 9.5 m (31.2 ft)
- Lanes
- 2
- Daily Traffic
- 30
- Material
- Concrete
- Design
- Stringer/Multi-beam or Girder
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $21,608,000
- Total Project Cost
- $32,412,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.