PINE GROVE ROAD over WILLEO CREEK
AT W ROSWELL CITY LIMITS · County 121, Georgia · Built 2002 · 2 Lanes · 10,300 vehicles/day
Overall
Deck
7
Good
Superstructure
8
Very Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 8 | Very Good |
| Substructure | 7 | Good |
Location
34.025939, -84.401017
This bridge is in worse condition than 15.6% of bridges in County 121. The average bridge in Georgia is 0 years old; this one is 24 years old.
Nearby Bridges
POST OAK TRITT ROA over WILLEO CREEK TRIB.
Built 2008
POST OAK TRITT ROA over WILLEO CREEK
Built 1983
JONES ROAD over WILLEO CREEK
Built 1968
MABRY ROAD over SWEAT MOUNTAIN CREEK
Built 1976
SR 120 over WILLEO CREEK
Built 1937
MARIETTA HIGHWAY over CHATTAHOOCHEE RIVER TRIB
Built 1991
AZALEA DRIVE over CHATTAHOOCHEE RIV TRIB
Built 1960
LOCH HIGHLAND PARK over SWEAT MOUNTAIN CREEK
Built 1977
CRABAPPLE ROAD over HOGWALLER CREEK
Built 1977
WESLEY CHAPEL ROAD over SWEAT MOUNTAIN CREEK
Built 1986
Bridge Details
- Structure #
- 000000012152960
- Year Built
- 2002
- Length
- 61 m (200.1 ft)
- Max Span
- 20.4 m
- Width
- 13 m (42.7 ft)
- Lanes
- 2
- Daily Traffic
- 10,300
- Material
- Prestressed Concrete
- Design
- Stringer/Multi-beam or Girder
- Owner
- City or Municipal Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $781,000
- Total Project Cost
- $1,172,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.