CENTRAL AVE. US 19 over I-75- 2 I-75 RAMPS
0.4 MI N CLAYTON CO LINE · County 121, Georgia · Built 1984 · 6 Lanes · 12,500 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
7
Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 7 | Good |
| Substructure | 7 | Good |
Location
33.652953, -84.396067
This bridge is in worse condition than 67.7% of bridges in County 121. The average bridge in Georgia is 0 years old; this one is 42 years old.
Nearby Bridges
PORSCHE AVENUE over I-75 NBCD SBCD
Built 1984
LP RD RAMP TO I-75 over MUD CREEK
Built 1984
I-75 RAMP TO I75 S over I-75 RAMP TO I-285 WBL
Built 1983
I-75 R TO LP RD & over MUD CREEK
Built 1984
R I-285W TO I-75S& over MUD CREEK
Built 1977
I-75 SB R TO I-285 over MUD CREEK
Built 1959
C W GRANT PKWY over I-75 (NBL) & CR 1511
Built 1984
AVIATON BOULEVARD over MUD CREEK
Built 1984
C W GRANT PKWY over I-75 (SBL) & I-75 RAMP
Built 1984
C W GRANT PKWY over I-75 RAMP TO I-285
Built 1984
Bridge Details
- Structure #
- 000000012100010
- Year Built
- 1984
- Length
- 118 m (387.1 ft)
- Max Span
- 25.3 m
- Width
- 26.7 m (87.6 ft)
- Lanes
- 6
- Daily Traffic
- 12,500
- Material
- Steel
- Design
- Stringer/Multi-beam or Girder
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $0
- Total Project Cost
- $0
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.