REDAN ROAD over SNAPFINGER CREEK
3.4 MI SE OF CLARKSTON · County 089, Georgia · Built 1940 · 5 Lanes · 17,900 vehicles/day
Overall
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 7 | Good |
| Substructure | 7 | Good |
Location
33.763328, -84.220336
This bridge is in worse condition than 34.9% of bridges in County 089. The average bridge in Georgia is 0 years old; this one is 86 years old.
Nearby Bridges
ROWLAND ROAD over INDIAN CREEK
Built 1963
INDIAN CREEK ROAD over INDIAN CREEK
Built 1935
PARK DRIVE over SNAPFINGER CREEK
Built 1950
INDIAN CREEK ROAD over SNAPFINGER CREEK TRIB
Built 1960
REDAN ROAD over I-285 (SR 407)
Built 1966
DURHAM PARK ROAD over INDIAN CREEK
Built 1979
I-285 RAMP TO MART over I-285 (SR 407)
Built 1992
KENSINGTON ROAD over MARTA
Built 1991
I-285 over M-9301 DURHAM PARK RD
Built 1966
COVINGTON HIGHWAY over I-285 (SR 407)
Built 2022
Bridge Details
- Structure #
- 000000008901890
- Year Built
- 1940
- Reconstructed
- 1992
- Length
- 27.4 m (89.9 ft)
- Max Span
- 9.1 m
- Width
- 23.9 m (78.4 ft)
- Lanes
- 5
- Daily Traffic
- 17,900
- Material
- Steel
- Design
- Stringer/Multi-beam or Girder
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $639,000
- Total Project Cost
- $959,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.