HOUSTON MILL ROAD over S FORK PEACHTREE CREEK

5.7 MI SE OF CHAMBLEE · County 089, Georgia · Built 1958 · 2 Lanes · 12,400 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
4
Poor
Superstructure
4
Poor
Substructure
6
Satisfactory

Bridge Details

Structure #
000000008901770
Year Built
1958
Length
54.9 m (180.1 ft)
Max Span
9.1 m
Width
11.6 m (38.1 ft)
Lanes
2
Daily Traffic
12,400
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$703,000
Total Project Cost
$1,055,000