CR 143 over 17 MILE RIVER
3.2 MI SW OF BROXTON · County 069, Georgia · Built 1960 · 2 Lanes · 519 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
7
Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 7 | Good |
| Substructure | 7 | Good |
Location
31.584639, -82.907142
This bridge is in worse condition than 92.9% of bridges in County 069. The average bridge in Georgia is 0 years old; this one is 66 years old.
Nearby Bridges
SR 206 over 17 MILE RIVER
Built 1962
MOSLEY ROAD over ROSES CREEK
Built 1980
NOAH MANCIL ROAD over HALLS CREEK
Built 1990
AMBROSE-BROXTON RD over ROSES CREEK
Built 2006
AMBROSE-BROXTON RD over HALLS CREEK
Built 2006
GEORGE DEEN ROAD over 9 MILE CREEK
Built 1954
SR 32 over CSX RAILROAD
Built 1969
SR 206 CONN. over 20 MILE CREEK TRIB.
Built 1977
BROXTON-WESTGREEN over 9 MILE CREEK
Built 1968
US 441 / SR 31 over 17 MILE RIVER
Built 1985
Bridge Details
- Structure #
- 000000006950070
- Year Built
- 1960
- Reconstructed
- 1996
- Length
- 31.1 m (102 ft)
- Max Span
- 6.1 m
- Width
- 7.7 m (25.3 ft)
- Lanes
- 2
- Daily Traffic
- 519
- Material
- Prestressed Concrete
- Design
- Channel Beam
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $399,000
- Total Project Cost
- $598,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.