GUY PAINE ROAD over NS RAILROAD
0.7 MI E OF SR 247 E MACO · County 021, Georgia · Built 1942 · 2 Lanes · 5,510 vehicles/day
Overall
Deck
7
Good
Superstructure
6
Satisfactory
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 6 | Satisfactory |
| Substructure | 6 | Satisfactory |
Location
32.780258, -83.6512
This bridge is in worse condition than 82.3% of bridges in County 021. The average bridge in Georgia is 0 years old; this one is 84 years old.
Nearby Bridges
US 41 NBL SR 19 over ROCKY CREEK
Built 2022
US 41 SBL SR19 over ROCKY CREEK
Built 2020
US 41 NBL SR 49 over ROCKY CREEK OVERFLOW
Built 2022
MEADE ROAD over NS RAILROAD
Built 1983
US 41 SBL SR 49 over ROCKY CREEK OVERFLOW
Built 2020
MEADE ROAD over NS RAILROAD
Built 1968
I-75 over SR 247 (US 41)(EXIT 160)
Built 1970
US 41 NBL SR 49 over TOBESOFKEE CREEK O/F
Built 2022
US 41 SBL SR 49 over TOBESOFKEE CREEK O/F
Built 2020
I-75 over M-3201 ROCKY CREEK ROAD
Built 1970
Bridge Details
- Structure #
- 000000002101860
- Year Built
- 1942
- Length
- 61.3 m (201.1 ft)
- Max Span
- 12.5 m
- Width
- 16.4 m (53.8 ft)
- Lanes
- 2
- Daily Traffic
- 5,510
- Material
- Concrete
- Design
- Tee Beam
- Owner
- City or Municipal Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $785,000
- Total Project Cost
- $1,178,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.