LIVE OAK CH ROAD over RED BLUFF CREEK

APP 7 MI SW OF PEARSON · County 003, Georgia · Built 1963 · 2 Lanes · 120 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
7
Good
Superstructure
7
Good
Substructure
4
Poor

Bridge Details

Structure #
000000000350150
Year Built
1963
Length
27.4 m (89.9 ft)
Max Span
9.1 m
Width
9.2 m (30.2 ft)
Lanes
2
Daily Traffic
120
Material
Concrete
Design
Tee Beam
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$352,000
Total Project Cost
$527,000