TOBEY HILL ROAD over WHITING RIVER

200 E OF CANAAN VALLEY R · County 005, Connecticut · Built 2021 · 2 Lanes · 257 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
8
Very Good

Bridge Details

Structure #
05205
Year Built
2021
Length
13.1 m (43 ft)
Max Span
11 m
Width
7.8 m (25.6 ft)
Lanes
2
Daily Traffic
257
Material
Prestressed Concrete
Design
Slab
Owner
Town or Township Highway Agency
Last Inspected
N/A
Est. Improvement
N/A
Total Project Cost
$2,500,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.