GARVEY AVE over RIO HONDO RIV

0.3MI W/O ROSEMEAD BLVD · County 037, California · Built 2008 · 4 Lanes · 23,520 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
5
Fair
Superstructure
4
Poor
Substructure
7
Good

Bridge Details

Structure #
53C2201
Year Built
2008
Length
128 m (419.9 ft)
Max Span
35.6 m
Width
29.3 m (96.1 ft)
Lanes
4
Daily Traffic
23,520
Material
Concrete
Design
Girder and Floorbeam System
Owner
City or Municipal Highway Agency
Last Inspected
N/A
Est. Improvement
$4,108,000
Total Project Cost
$6,901,000