SHORE ROAD over TEQUISQUITA CREEK
0.05 MI E FRAZER LAKE RD · County 069, California · Built 1948 · 2 Lanes · 6,500 vehicles/day
Structurally Deficient
— One or more key components rated 4 (Poor) or below
Overall
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
4
Poor
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 6 | Satisfactory |
| Substructure | 4 | Poor |
Location
36.942792, -121.444494
This bridge is in worse condition than 90.8% of bridges in County 069. The average bridge in California is 0 years old; this one is 78 years old.
Nearby Bridges
SHORE ROAD over TEQUISQUITA SLOUGH OVFL
Built 1950
LOVERS LANE over PACHECO CREEK
Built 1993
DUNNE LANE over PACHECO CREEK
Built 1986
SAN FELIPE ROAD over TEQUISQUITA SLOUGH
Built 1952
STATE ROUTE 152 over HOLSTEIN CREEK
Built 1993
SAN FELIPE ROAD over BRANCH OF SANTA ANA CRK
Built 1975
SAN FELIPE ROAD over SANTA ANA CREEK
Built 1975
FRAZIER LAKE ROAD over MILLERS CANAL
Built 1995
STATE ROUTE 156 over PACHECO CREEK
Built 1966
STATE ROUTE 156 over TEQUISQUITA SLOUGH
Built 1966
Bridge Details
- Structure #
- 43C0007
- Year Built
- 1948
- Length
- 28.2 m (92.5 ft)
- Max Span
- 8 m
- Width
- 9.1 m (29.9 ft)
- Lanes
- 2
- Daily Traffic
- 6,500
- Material
- Concrete Continuous
- Design
- Slab
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $588,000
- Total Project Cost
- $989,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.