N FANCHER AVE over MILL DITCH
0.3 MI SOUTH OF MCKINLEY · County 019, California · Built 1939 · 2 Lanes · 200 vehicles/day
Structurally Deficient
— One or more key components rated 4 (Poor) or below
Overall
Deck
7
Good
Superstructure
4
Poor
Substructure
4
Poor
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 4 | Poor |
| Substructure | 4 | Poor |
Location
36.760744, -119.632464
This bridge is in worse condition than 96.4% of bridges in County 019. The average bridge in California is 0 years old; this one is 87 years old.
Nearby Bridges
N FANCHER AVE over FANCHER CREEK CANAL
Built 1948
E MCKINLEY AVE over MILL DITCH
Built 1994
N DE WOLF AVE over MILL DITCH
Built 1940
N LEONARD AVE over REDBANK SLOUGH
Built 1997
N MCCALL AVE over FRESNO CANAL
Built 1953
N MCCALL AVE over GOULD CANAL
Built 1925
N HIGHLAND AVE over GOULD CANAL
Built 1932
E BELMONT AVE over FANCHER CREEK CANAL
Built 1956
LEONARD AVE over GOULD CANAL
Built 2019
N MCCALL AVE over REDBANK SLOUGH
Built 1925
Bridge Details
- Structure #
- 42C0519
- Year Built
- 1939
- Reconstructed
- 1960
- Length
- 12.2 m (40 ft)
- Max Span
- 6.1 m
- Width
- 7.3 m (24 ft)
- Lanes
- 2
- Daily Traffic
- 200
- Material
- Wood or Timber
- Design
- Stringer/Multi-beam or Girder
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $204,000
- Total Project Cost
- $343,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.