INTERSTATE 280 NB over SAN FRANCISQUITO CREEK

04-SM-280-R0.30 · County 081, California · Built 1969 · 5 Lanes · 46,500 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
4
Poor
Superstructure
5
Fair
Substructure
7
Good

Bridge Details

Structure #
35 0234R
Year Built
1969
Length
74.7 m (245.1 ft)
Max Span
25.3 m
Width
20.6 m (67.6 ft)
Lanes
5
Daily Traffic
46,500
Material
Concrete Continuous
Design
Box Beam or Girders - Multiple
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$1,539,000
Total Project Cost
$2,585,000