AL 157 over I65

JCT I65 * SR 157 · County 043, Alabama · Built 1965 · 5 Lanes · 16,718 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
6
Satisfactory

Condition Ratings

ComponentRatingDescription
Deck 6 Satisfactory
Superstructure 6 Satisfactory
Substructure 6 Satisfactory

Location

34.207456, -86.878636

This bridge is in worse condition than 50.8% of bridges in County 043. The average bridge in Alabama is 0 years old; this one is 61 years old.

Nearby Bridges

Bridge Details

Structure #
015027
Year Built
1965
Reconstructed
1990
Length
91.1 m (298.9 ft)
Max Span
25 m
Width
25.4 m (83.3 ft)
Lanes
5
Daily Traffic
16,718
Material
Concrete Continuous
Design
Tee Beam
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$5,735,000
Total Project Cost
$6,309,000