US 231 over GOVERNORS DR * BRANCH
JCT GOVERNORS DR * US 231 · County 089, Alabama · Built 1978 · 4 Lanes · 83,768 vehicles/day
Overall
Deck
5
Fair
Superstructure
6
Satisfactory
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 5 | Fair |
| Superstructure | 6 | Satisfactory |
| Substructure | 6 | Satisfactory |
Location
34.719897, -86.592528
This bridge is in worse condition than 83% of bridges in County 089. The average bridge in Alabama is 0 years old; this one is 48 years old.
Nearby Bridges
RAMP 45 TO I565 over I-565; SR 20
Built 1989
RAMP 43 AIRPORT R over I565
Built 1989
SR53;GOVERNORS DR over PINHOOK CREEK
Built 1962
US231; US431; SR1 over HUNTSVILLE SPRING BRANCH
Built 1977
US231; US431; SR1 over HUNTSVILLE SPRING BRANCH
Built 1977
SR 53 over STREAM
Built 1977
SR53;GOVERNORS DR over BROGLAN BRANCH
Built 1962
SEMINOLE DR over BROGLAN BRANCH
Built 1972
MONROE STREET over FAGAN CREEK
Built 2004
MONROE AVE over BIG SPRING LAGOON
Built 2004
Bridge Details
- Structure #
- 011957
- Year Built
- 1978
- Length
- 221.6 m (727 ft)
- Max Span
- 43.6 m
- Width
- 28.1 m (92.2 ft)
- Lanes
- 4
- Daily Traffic
- 83,768
- Material
- Steel
- Design
- Stringer/Multi-beam or Girder
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $13,979,000
- Total Project Cost
- $15,377,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.