AL 126 over I85

WAUGH EXIT · County 101, Alabama · Built 1962 · 2 Lanes · 4,240 vehicles/day

Overall
Fair
Deck
5
Fair
Superstructure
6
Satisfactory
Substructure
6
Satisfactory

Condition Ratings

ComponentRatingDescription
Deck 5 Fair
Superstructure 6 Satisfactory
Substructure 6 Satisfactory

Location

32.36865, -86.052606

This bridge is in worse condition than 81.2% of bridges in County 101. The average bridge in Alabama is 0 years old; this one is 64 years old.

Nearby Bridges

Bridge Details

Structure #
007563
Year Built
1962
Length
75.3 m (247 ft)
Max Span
20.7 m
Width
10.1 m (33.1 ft)
Lanes
2
Daily Traffic
4,240
Material
Concrete Continuous
Design
Tee Beam
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$1,935,000
Total Project Cost
$2,129,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.